Allana Buick & Bers, Inc. (ABB) was retained to perform investigation, design and construction monitoring services to re-roof Hilgard Hall at the UC Berkeley campus.

ABB performed a roof survey and balcony and laboratory test on this original University of California building. ABB scope of work included exterior fresco wall restoration, sealing and common area roof decks. ABB used the existing clay tile roofs manufactured in 1918 on the new roof. New copper gutters to match the existing 1918 gutters were installed.

The scope of work also included preparation of construction documents, construction administration and monitoring. ABB also provided investigation and assessment of stair landing leaks, and recommendations for repair.

Hilgard Hall is listed in the National Register of Historic Places.